September 2013 -> November 2013

In December 2013 we completed the earthworks and concrete works for the “Shaking Tables concrete structure extension” for Talison Lithium in Greenbushes.

Our direct clients were MSP Engineering.

Included in the project scope was:

  • ~ 300m3 Excavation for main Raft footing.
  • 1. Blinding, 2. Steel fixing and 3. Concreting of this footing.
  • Concrete plinth and “up stand” construction
  • Holding Down bolt supply and installation.
  • Column and “Suspended slab” construction including temporary works design. Once again we completed our scope ahead of programme with a flawless safety record.